- Other charges associated with metering alterations, approvals or commissioning and testing are not included in pre-approval charges.
- If any adverse impacts to the network are identified, the capacity of the proposed system might need to be reduced, export limitation may be proposed, connection may be refused, or a financial contribution may be required to upgrade the electricity network.
- Embedded Generation systems that do not meet the minimum requirements as set out in applicable policies and guidelines will not be accepted, and when identified will be required to disconnect until modified to comply.
- AusNet Services monitors the export of embedded generation systems to ensure that the agreed installation capacity and export limits are not breached. Where breaches are identified, the Embedded Generation system will be required to disconnect until modified to comply.